Week 3

Monday

W3Mon04Early.JPG (47915 bytes)

Team 2 (some of them) down early on the site to get set up

W3Tue17.JPG (38966 bytes)

 

W3Mon02.JPG (53728 bytes) W3Mon01.JPG (57352 bytes)

The second team arrived safely and are already laying block!

 

W3Mon03.JPG (57802 bytes) W3Mon04.JPG (55127 bytes)

Scaffolding is being set up so block can be laid right to the "ring beam."


Tuesday

W3Tue01.JPG (51761 bytes)

Both ends up to the "ring beam!"

W3Tue02.JPG (61738 bytes) W3Tue04.JPG (56619 bytes)

It's a full time job for several fellows just to keep block and mortar
flowing to the 4 - 5 block layers working all at once!

W3Tue06.JPG (55069 bytes)

Brian cutting/custom fitting block

W3Tue05.JPG (50818 bytes) W3Tue10.JPG (55955 bytes)

Kevin & Crew laying block - - Louis and Mr. Chaney "feeding" the block layers

 

W3Tue08.JPG (65530 bytes)

Mr. Chaney, Louis and Eric
...watch out fellows, there's no railing yet!

 

W3Tue11.JPG (54654 bytes) W3Tue04.JPG (56619 bytes)

Joseph and Pat taking a breather - it's hot!

 

W3Tue26.JPG (43655 bytes) W3Tue03.JPG (64852 bytes)

W3Tue12.JPG (49939 bytes)

Loius, what did you do with the door?


Wednesday

Barnard02.JPG (42775 bytes) PatSax03.JPG (45567 bytes)

Pastor Barnard Preaching at Windward Bible Church (L)
Pat Murphy playing the Saxophone (R)

Pastor Sullivan preached at the Grand Bay Gospel Hall (Brethren assembly) and
Pastor Chaney preached at Open Door Baptist Church


Thursday

W3Thu06.JPG (52009 bytes)

Thursday started off with rain... lots of it...
Louis, Frank & Eric covering the block to keep them dry

- you can't lay wet block!

W3Thu05.JPG (47859 bytes) W3Thu04.JPG (42106 bytes)

...plan "B"... fill periodic beams and the bond beam...

W3Thu03.JPG (35878 bytes)

Herman is way up there!

 

W3Thu02.JPG (53276 bytes)W3Thu01.JPG (48791 bytes)

Kevin, John & Eric making concrete

 

W3Thu07.JPG (42216 bytes)

Frank Sullivan looking for "higher ground."

W3Thu08b.jpg (38191 bytes)

WOW!
These guys have been busy today!


Friday

W3Fri04.JPG (58672 bytes)

Here is the "Week3" Team (+Mervin)
Mervin, Robert, John, Frank, Kevin, Loius, Brian, Herman, Eric, Ray, Joe & Doug
(Mervin, on the left, is the local contractor who put in the foundation.
He happened by for a look while we were taking the picture so we asked him to join in.)

Kitchen staff this week (no picture yet) has been
Barbara, Heather, Amiee & Sarah

 

W3Fri05.JPG (51308 bytes)

All four exterior walls finished, concrete filled columns included!

Praise the Lord!

Several of the men on this team leave in the morning (Saturday) to return home. 
Several more will join us on Sunday.

Look for "Week 4" for more pictures and progress!

 

 